GI motorised rolling shutters installed at Flipkart warehouse in Jodhpur
Case Study

Flipkart Warehouse Rolling Shutter Project — GRS Case Study

7 Jun 2026 · 7 min read · By Goyal Rolling Shutters
Table of Contents
  1. Project Brief
  2. The Challenge
  3. Specification Selected
  4. Delivery & Installation
  5. Outcomes
  6. Learnings

When Flipkart's logistics infrastructure team required rolling shutters for two new fulfilment centre expansions — in Jodhpur, Rajasthan, and Bilaspur, Chhattisgarh — they needed a manufacturer who could supply custom-sized heavy-duty units, install across two geographically distant sites on a coordinated timeline, and complete the work before go-live dates fixed by Flipkart's operations calendar.

This is a detailed account of how GRS approached that project — the specification decisions, the logistical challenges, and what we would do the same or differently on a similar project today.

Project Brief

2
Warehouse Sites
40+
Shutters Installed
18
Days to Completion
ParameterJodhpur SiteBilaspur Site
Facility typeFlipkart fulfilment centreFlipkart logistics hub
LocationIndustrial area, Jodhpur, RajasthanIndustrial area, Bilaspur, CG
Opening count18 dock bays + 6 side access12 dock bays + 4 side access
Shutter typeGI motorised, heavy-dutyGI motorised, heavy-duty
Go-live deadlineFixed (operations calendar)Fixed (operations calendar)

The Challenge

Three specific challenges made this project non-trivial:

1. Non-standard opening sizes

Flipkart's warehouse structural drawings specified dock bay openings at 4,800mm × 5,200mm — a non-standard size that most suppliers would need 4–6 weeks to fabricate. The side access openings were 3,200mm × 3,500mm. Both required custom drum sizing and twin-motor configuration for the larger bays.

2. Two-site simultaneous delivery

Jodhpur and Bilaspur are 1,200km apart. Delivering to both sites within a 3-day window required coordinated logistics from our Delhi workshop — two separate dispatch batches with staggered loading schedules and site-specific installation crews deployed in parallel.

3. Rajasthan summer heat

The Jodhpur installation ran in late April–May, with ambient temperatures reaching 46°C. Motor selection had to account for the reduced motor efficiency at high ambient temperatures — standard commercial motors begin thermal derating above 40°C. This required specifying motors with a higher base torque rating than the curtain weight calculation alone would indicate.

Specification Selected

Dock Bay Shutters — 4,800 × 5,200mm

  • Curtain 0.8mm Z275 galvalume steel, 77mm C-profile
  • Configuration Twin motor (one per side) — required for 4,800mm+ widths
  • Motor FAAC D600 — 600 Nm output, heavy industrial duty
  • Spring Heavy-duty galvanised torsion, rated 100,000 cycles
  • Guide rails 100mm deep galvanised steel (upgraded from standard 75mm for wind load)
  • Wind bars 2 × mid-span stiffeners per curtain (Jodhpur desert wind zone)
  • Bottom bar Double-lip EPDM seal with aluminium carrier extrusion
  • Motor thermal rating 55°C ambient (standard for Rajasthan summer)

Side Access Shutters — 3,200 × 3,500mm

  • Curtain 0.8mm Z275 galvalume steel, 77mm C-profile
  • Motor FAAC D300 — 300 Nm single motor
  • Spring Commercial galvanised torsion, rated 50,000 cycles
  • Guide rails 75mm galvanised steel
  • Controls Key switch + radio remote + provision for future security system interface

Motor specification decision: For the Jodhpur dock bays, we specified the FAAC D600 at 600 Nm despite the curtain weight calculation indicating 400 Nm would be technically sufficient. The 50% torque margin was deliberate — accounting for spring tension loss over time, peak summer ambient derating, and the high cycle count expected at a Flipkart fulfilment centre (40–80 cycles per bay per day). Undersizing here would have meant motor replacement within 18 months.

Delivery & Installation

Total fabrication time from order confirmation to dispatch: 14 working days. This required running both sites' curtain fabrication in parallel at our Delhi workshop — two separate production schedules sharing the same fabrication floor.

Dispatch sequence:

  1. Day 14: Jodhpur batch dispatched — 24 shutter units, 2 trucks. Transit time: 10 hours to Jodhpur site.
  2. Day 15: Bilaspur batch dispatched — 16 shutter units, 1 truck. Transit time: 18 hours to Bilaspur site.
  3. Day 15–18: Jodhpur installation crew (5 technicians): 24 units installed in 4 days working extended hours to meet go-live.
  4. Day 16–18: Bilaspur installation crew (3 technicians): 16 units installed in 3 days.
  5. Day 18: Both sites completed and signed off. Operations go-live on schedule.

"Two sites, 40 shutters, 18 working days from order to sign-off. The logistics coordination was as important as the fabrication."

Outcomes

Both facilities went live on schedule. Specific outcomes reported by Flipkart's facilities team:

  • All 40 shutters operational at go-live — no snags requiring post-handover corrections.
  • Zero motor failures in the 12 months following installation (Flipkart conducted a 12-month review).
  • The twin-motor dock bay shutters were noted by the operations team as particularly reliable — consistent open/close times even under high-cycle use during peak dispatch periods (Diwali season).
  • Jodhpur motors maintained performance through summer — the 55°C ambient rating proved its value during the peak June heat.

Learnings — What We Would Do the Same, and What We Changed

Keep: Motor torque margin for large industrial projects

Specifying 50% above the calculated minimum torque requirement on high-cycle industrial applications has become our standard practice for any project with projected cycle counts above 40 per day. The premium over base specification is modest (8–12% of motor cost) and the reliability gain is significant.

Change: Phased delivery communication

Managing two simultaneous site deliveries revealed gaps in our communication protocol. We now require a dedicated site coordinator for multi-location projects — a single point of contact who tracks both dispatch and installation progress across sites in real time.

Keep: Wind bar specification for desert zone

Jodhpur's Loo winds (hot desert winds reaching 80–100 km/h in summer) require wind bars on any curtain above 3,000mm in width. The additional cost is minimal (₹1,800–2,500 per curtain) and the alternative — curtain billowing and guide rail damage — would have been costly to repair.

GRS
Goyal Rolling Shutters — Projects Team

GRS has delivered multi-site rolling shutter projects for major Indian retailers, logistics operators, and government institutions since 1985. Contact us for multi-site project consultation and programme planning.

Multi-site delivery · Coordinated installation crews · Fixed-timeline projects

Multi-site rolling shutter project? We've done it before.

GRS manages the full project cycle for multi-site clients — fabrication scheduling, coordinated dispatch, parallel installation crews, and a single point of contact. Get a consultation call within 24 hours.